New Delhi: Crude Oil: Crude oil production during August, 2016 was 3067.80 TMT which is 1.02% and 3.93% lower than target and production achieved in August 2015 respectively. Cumulative crude oil production during April-August, 2016 was 15146.22 TMT which is 0.75% and 3.15% lower than target and production during corresponding period of last year respectively. Unit-wise and state-wise crude oil production is given at Annexure-I. Unit-wise crude oil production for the month of August, 2016 and cumulatively for the period April-August, 2016 vis-à-vis same period of last year has been shown in Table-1 and month-wise in Figure-1.
Table-1: Crude Oil Production (in TMT)
Oil Company | Target | August (Monthly) | April-August (Cumulative) | ||||||
2016-17 (Apr-Mar) | 2016-17 | 2015-16 | % over last year | 2016-17 | 2015-16 | % over last year | |||
Target | Prod.* | Prod. | Target | Prod.* | Prod. | ||||
ONGC | 22766.00 | 1897.03 | 1865.31 | 1929.26 | 96.69 | 9339.92 | 9225.22 | 9384.57 | 98.30 |
OIL | 3480.00 | 276.32 | 272.08 | 276.02 | 98.57 | 1345.26 | 1342.94 | 1388.15 | 96.74 |
PSC Fields | 10839.32 | 926.13 | 930.42 | 987.86 | 94.19 | 4576.01 | 4578.05 | 4865.61 | 94.09 |
Total | 37085.32 | 3099.48 | 3067.80 | 3193.15 | 96.07 | 15261.20 | 15146.22 | 15638.33 | 96.85 |
Figure-1: Monthly Crude Oil Production
Unit-wise production details with reasons for shortfall have been given in following sub-sections:
1.1 Crude oil production by ONGC during August, 2016 was 1865.31 TMT which is 1.67% lower than the monthly target and 3.31% less when compared with August, 2015. Cumulative crude oil production during April-August, 2016 was 9225.22 TMT which is 1.23% lower than target for the period and 1.70% lower than the production during corresponding period of last year. Reasons for shortfall in production in some fields are as under:
- Repair of sub-sea leakage in well fluid lines and less than planned production from Marginal fields
- Repair of sub-sea leakage in 16″ HSC–HRG well fluid line
1.2 Crude oil production by OIL during August, 2016 was 272.08 TMT which is 1.54% lower than monthly target and 1.43% less than production in August 2015. Cumulative crude oil production during April-August, 2016 was 1342.94 TMT which is 0.17% lower than target for the period and 3.26% lower than the production during corresponding period of last year. Reasons for shortfall in production are as under:
- Less than planned contribution from old wells.
- Rise in water cut in wells of Greater Hapjan, Greater Chandmari fields & Naharkatiya fields.
- Loss in production of 2622 MT on account of strike by drivers during 15th to 18th Aug’16, bomb blasts at Tinsukia, Dibrugarh and Sibsagar districts on 14th & 15th Aug’16 and miscreant activities/local problems at various locations during the month.
1.3 Crude oil production by Pvt. /JVs during August 2016 was 930.42 TMT which is 0.46% higher than the monthly target but 5.81% less when compared with August, 2015. Cumulative crude oil production during April-August, 2016 was 4578.05 TMT which is marginally higher (0.04%) than target for the period and 5.91% lower than the production during corresponding period of last year. Reasons for shortfall in production are as under:
- Natural Decline in Ravva, CB-OS/2 and well fluid riser problems in Panna-Mukta
- Closure of one well in MA and one well in D1D3 field in KG-DWN-98/3
- Underperformance of Bhagyam field and natural decline of Mangala wells of RJ-ON-90/1
Natural Gas
- Natural gas production during August, 2016 was 2674.15 MMSCM which is 4.90% lower than the target for the month and 5.72% lower than the production in August, 2015. Cumulative natural gas production during April-August, 2016 was 13123.44 MMSCM which is 3.27% lower than target for the period and 4.20% lower than the production during corresponding period of last year. Unit-wise and state-wise natural gas production is given at Annexure-II. Unit-wise natural gas production for the month of August, 2016 and cumulatively for the period April-August, 2016 vis-à-vis same period of last year has been shown in Table-2 and month-wise in Figure-2.
Table-2: Natural Gas Production (MMSCM)
Oil Company | Target | August (Monthly) | April-August (Cumulative) | ||||||
2016-17 (Apr-Mar) | 2016-17 | 2015-16 | % over last year | 2016-17 | 2015-16 | % over last year | |||
Target | Prod.* | Prod. | Target | Prod.* | Prod. | ||||
ONGC | 22743.43 | 1877.46 | 1845.51 | 1855.82 | 99.44 | 8964.30 | 8841.63 | 9022.49 | 98.00 |
OIL | 2950.03 | 257.03 | 244.05 | 242.66 | 100.57 | 1265.79 | 1230.88 | 1116.89 | 110.21 |
PSC Fields | 8425.44 | 677.35 | 584.59 | 737.88 | 79.23 | 3337.48 | 3050.93 | 3559.40 | 85.71 |
Total | 34118.90 | 2811.85 | 2674.15 | 2836.36 | 94.28 | 13567.57 | 13123.44 | 13698.78 | 95.80 |
*: Provisional
Figure-2: Monthly Natural Gas Production
2.1 Natural gas production by ONGC during August, 2016 was 1845.51 MMSCM which is 1.70% lower than the monthly target and 0.56% lower when compared with August, 2015. Cumulative natural gas production during April-August, 2016 was 8841.63 MMSCM which is 1.37% lower than the cumulative target and 2.0% lower than the production during the corresponding period of last year. Reasons for shortfall in production are as under:
- Natural decline from Bassein field and restricted withdrawal of gas by GAIL in EOA
2.2 Natural gas production by OIL during August, 2016 was 244.05 MMSCM which is 5.05% lower than the monthly target but 0.57% higher than August 2015. Cumulative natural gas production during April-August, 2016 was 1230.88 MMSCM which is 2.76% lower than the cumulative target but 10.21% higher than the production during the corresponding period of last year. Reasons for shortfall in production are as under:
- Loss in gas production potential on account of water loading of high potential wells, unexpected subsurface problems
2.3 Natural gas production by Pvt. /JVs during August 2016 was 584.59 MMSCM which is 13.70% lower than the monthly target and 20.77% less when compared with August, 2015. Cumulative natural gas production during April-August, 2016 was 3050.93 MMSCM which is 8.59% lower than the cumulative target and 14.29% lower than the production during the corresponding period of last year. Reasons for shortfall in production are as under:
- Underperformance of KG-OSN-2001/3
- Increase in water cut in few wells in RJ-ON/6
- Underperformance of Raniganj East, Sohagpur West & Raniganj South CBM blocks
- Closure of one well each in MA and D1D3 in KG-DWN-98/3
- Increase in water cut in few wells in RJ-ON/6
Refinery Production (in terms of Crude oil processed)
3 Refinery production during August, 2016 was 20290.26 TMT which is 2.32% higher than the target for the month and 3.46% higher than the production during corresponding period of last year. Cumulative production during April-August, 2016 was 101784.38 TMT which is 3.35% higher than the target for the period and 7.64% higher than the production during corresponding period of last year. Unit-wise production is given at Annexure-III. Unit-wise production for the month of August, 2016 and cumulatively for the period April-August, 2016 vis-à-vis same period of last year has been shown in Table-3 and month-wise in Figure-3.
Table 3: Refinery Production (TMT)
Oil Company | Target | August (Month) | April-August (Cumulative) | ||||||
2016-17 (Apr-Mar) | 2016-17 | 2015-16 | % over last year | 2016-17 | 2015-16 | % over last year | |||
Target | Prod.* | Prod. | Target | Prod.* | Prod. | ||||
A. Public Sector | 135565.03 | 10894.00 | 10985.15 | 10296.55 | 106.69 | 55625.78 | 56599.40 | 50938.73 | 111.11 |
IOCL | 65100.00 | 5410.30 | 4953.45 | 4558.39 | 108.67 | 26634.68 | 26736.96 | 22875.57 | 116.88 |
BPCL | 25250.15 | 2049.97 | 2150.36 | 2033.01 | 105.77 | 10211.48 | 10485.93 | 10142.12 | 103.39 |
HPCL | 16800.29 | 1147.31 | 1253.23 | 1551.45 | 80.78 | 6925.89 | 7152.95 | 6465.36 | 110.63 |
CPCL | 10250.00 | 951.11 | 1006.67 | 549.16 | 183.31 | 4599.35 | 4645.52 | 4148.96 | 111.97 |
NRL | 2670.00 | 231.37 | 239.04 | 252.93 | 94.51 | 1142.44 | 1163.62 | 918.56 | 126.68 |
MRPL | 15450.00 | 1100.00 | 1376.01 | 1349.04 | 102.00 | 6095.00 | 6380.13 | 6366.61 | 100.21 |
ONGC | 44.59 | 3.95 | 6.40 | 2.56 | 250.14 | 16.94 | 34.29 | 21.54 | 159.16 |
B. Joint Venture | 15000.00 | 1246.02 | 1521.60 | 1557.55 | 97.69 | 6478.73 | 7358.10 | 7002.52 | 105.08 |
BORL | 6000.00 | 450.00 | 587.60 | 620.19 | 94.74 | 2550.00 | 2771.82 | 2425.00 | 114.30 |
HMEL | 9000.00 | 796.02 | 934.00 | 937.36 | 99.64 | 3928.73 | 4586.28 | 4577.52 | 100.19 |
C. Private Sector | 89852.65 | 7689.74 | 7783.51 | 7757.64 | 100.33 | 36385.32 | 37826.87 | 36616.40 | 103.31 |
RIL | 69561.01 | 5998.74 | 6002.57 | 5998.74 | 100.06 | 27930.35 | 29068.16 | 27930.35 | 104.07 |
EOL | 20291.64 | 1691.00 | 1780.94 | 1758.90 | 101.25 | 8454.97 | 8758.71 | 8686.05 | 100.84 |
TOTAL (A+B+C) | 240417.68 | 19829.76 | 20290.26 | 19611.74 | 103.46 | 98489.83 | 101784.38 | 94557.65 | 107.64 |
*: Provisional
Figure 3: Monthly Refinery Production
3.1 PSU Refineries’ production during August, 2016 was 10985.15 TMT which is 0.84% higher than the target for the month and 6.69% higher than the production achieved in the corresponding month of last year. Cumulative production during April-August, 2016 was 56599.40 TMT which is 1.75% higher than the target for the period and 11.11% higher than the production during corresponding period of last year. Reasons for shortfall of refinery production in some PSU refineries are as under:
- IOCL, Guwahati & Digboi: Lower crude availability.
- IOCL, Panipat: Throughput is restricted due to advancement of planned shut-down of Diesel Hydro Treatment unit.
- IOCL, Paradip: Throughput is lower due to delay in commissioning of South oil jetty and Continuous Catalytic Reforming Unit under shut-down for maintenance.
3.2 Production in JV refineries during August, 2016 was 1521.60 TMT which is 22.12% higher than the target for the month but 2.31% lower than the production achieved in the corresponding month of last year. Cumulative production during April-August, 2016 was 7358.10 TMT which is 13.57% higher than the target for the period and 5.08% higher than the production during corresponding period of last year.
3.3 Production in private refineries during August, 2016 was 7783.51 TMT which is 1.22% higher than the target for the month and 0.33% higher than the production achieved in the corresponding month of last year. Cumulative production during April-August, 2016 was 37826.88 TMT which is 3.96% higher than the target for the period and 3.31% higher than the production during corresponding period of last year.
3.4 Refinery-wise details of the capacity utilization and production of petroleum products during the month of August, 2016 and cumulatively for the period April-August, 2016 vis-à-vis April-August, 2015 are given at Annexures-IV and V respectively.
- Figures of percentage growth of Public Sector Refineries in the monthly report for July 2016 were printed incorrectly, which is regretted.Modified Table 3 also incorporating targets of Refinery Production, since finalised, is at Annexure VI. .