New Delhi: Ministry of Railways approved the following Projects:-
1. Project of Doubling of Jaunpur- Akbarpur (Tanda).- Northern Railway.
2. Project of Doubling of New Maynaguri-Gumanihat (51.65km) in Northeast Frontier Railway.
3. Project of Etawah Flyover 10.978 km in North Central Railway.
Salient Features of Projects Approved:-
1. Project Doubling of Jaunpur- Akbarpur (Tanda).- Northern Railway
Decision |
: |
Sanction of project of doubling of Jaunpur- Akbarpur (Tanda) 77.25 km long section in Northern Railways |
Background |
: |
The Jaunpur-Akbarpur section falls in Lucknow Division of Northern Railways. At present detention of trains in Jaunpur-Akbarpur is high (140 minutes) as 31 trains are running on single line section. Present capacity utilization is 133%. Also 14 more freight trains are expected each day with augmentation of National Thermal Power Corporation plant at Tanda by January, 2019.Doubling is absolutely necessary and it would not only speed up operation of goods and passenger trains but will also provide additional capacity for meeting the increased traffic in future. |
Strategy and targets |
: |
(i) Anticipated cost of Rs 676.36 crore with completion cost of Rs 766.33 crore of the project is proposed to be funded through Gross Budgetary Support (ii) This project is scheduled for completion by 2021-22 |
Expenditure Involved |
: |
Rs 676.36 Cr |
States/Districts covered |
: |
Jaunpur, Ambedkar Nagar in Uttar Pradesh |
2. Project of doubling of New Maynaguri-Gumanihat (51.65km) in Northeast Frontier Railway
Decision |
: |
Sanction of Project of doubling of New Maynaguri-Gumanihat (51.65km) in Northeast Frontier Railway
|
Background |
: |
The project section is a part of Malda-Guwahati Main line route. For the route connecting to North East region this is the only 51 km patch left for doubling and it is necessary for overall development of the region and to reap the benefits of other doubling projects and gauge conversion projects completed in the section. The line capacity utilization of the section between Raninagar Jalpaiguri to Samuktala Road is 145.70% with maintenance block during 2016-17. At present, 38 trains are running against the sectional capacity of 22 trains. Doubling is therefore absolutely necessary to speed up operation of goods and passenger trains and for overall development of the region. |
Strategy and targets |
: |
(i) Anticipated cost of Rs 602.27 crore with completion cost of Rs 648.19 crore of the project is proposed to be funded through Gross Budgetary Support (ii) This project is scheduled for completion by 2020-21
|
Expenditure Involved |
: |
Rs 602.27 Cr |
States/Districts covered |
: |
Jalpaiguri and New Coochbehar in West Bengal |
3. Project of Etawah Flyover 10.978 km in North Central Railway
Decision |
: |
Sanction of Etawah Flyover 10.978 km in North Central Railway |
Background |
: |
This flyover will help in avoiding surface crossing on busy Delhi Howrah route and will help in reducing detentions and removing bottlenecks. Trains coming from Gwalior/Agra to Etawah will move via flyover over UP & DN lines. Trains from Gwalior/Agra and going to Mainpuri will move via flyover and branch off to Mainpuri. Trains coming from Etawah and going to Mainpuri will move via flyover, over the UP & DN main lines. This flyover at Etawah will help in improving punctuality of passenger trains and smooth running of the routes i.e. Howrah- Kanpur-New Delhi, Etawah –Bhind & Agra and Etawah- Mainpuri. |
Strategy and targets |
: |
(i) Anticipated cost of Rs 830.73 crore with completion cost of Rs 894.47 crore of the project is proposed to be funded through Gross Budgetary Support (ii) This project is scheduled for completion by 2020-21 |
Expenditure Involved |
: |
Rs 830.73 Cr |
States/Districts covered |
: |
Etawah, Uttar Pradesh |